Khayamnandi Construction Plan - Port Elizabeth. Construction proposalByKaba Herbert Kabagame
KHAYAMNANDI:
PROPOSAL FOR COMMENCEMENT OF RAPID HOUSING CONSTRUCTION
JANUARY 2016
LOCATION
The greater Khayamnandi
Development project is located in Ward 41 of the Nelson Mandela Bay
Municipality and lies between Despatch, Booysen Park, Joe Slovo and Bloemendal.
NATURE AND SCALE
The project is
designed to be rolled out in 11 phases and to yield a total of:
- 12,040 residential units (8538 individual erven & 3502 high density)
- 28 Churches
- 20 Business
- 15 Crèches
- 13 Schools
- 5 Clinics
SERVICING PROGRESS (USDG)
To date, phase 1,2
and 3 have been serviced - yielding a total of 1879 sites.
The breakdown is as
follows;
- 660 phase 1A & 1B
- 1013 phase 2
- 206 phase 3
(see diagram 1)
TOP-STRUCTURE
HISTORY (HSDG)
In August 2013,
NMBM submitted an HSDG application to the Provincial Department of Human
Settlements for 184 subsidies/units totalling to R 14,167,000 – amounting to R
76,994.61 per unit (annexure 1)
On 23 July 2013
PDoHS wrote a letter to NMBM notifying it of the approval of 179
subsidies/units with a budget of R 15,739,278.00 - amounting to R87,928.93 per
unit (annexure 2).
A further R 244,487.15 was approved for relocation
(R1,365.85 per erf). It is yet to be established why the approval was for 179
and not 184 subsidies/units. On 20 March 2015, PDoHS sent another letter
approving a further R 5,945,819 – representing the subsidy adjustment
provision.
Despite the
approvals reflected above, no proof has been obtained that NMBM followed up by
way of obtaining the funds and/or commissioning of the construction of the
housing units in Khayamnandi 184.
Diagram1: Servicing progress
BUCKET ERADICATION PROGRAMME
NMBM was able – via the Provincial Treasury – to access funding from the
Bucket Eradication Programme to invest in Khayamnandi. The Province appointed
Coega Development Corporation (CDC) as Implementing Agent for the project.
The
following aspects are worth noting;
(i) to date 1671 foundation
& toilet structures have been erected (diagram 2)
(ii) each foundation is 42 square meters – 40
being for the house and 2 as a stoep.
(iii) of the 1671 structures that are
completed, 1625 have been certified and 586 have got beneficiaries on site
residing in shacks (table 1)
Total
sites
|
Complete
foundation
|
Foundations
certified
|
Toilets
completed
|
Beneficiaries
on site
|
Undeveloped
sites
|
|
Phase
1
|
658
|
650
|
638
|
648
|
586
|
5
|
Phase
2
|
1013
|
1004
|
987
|
1004
|
0
|
9
|
TOTAL
|
1671
|
1654
|
1625
|
1652
|
586
|
14
|
Table 1: construction
status and beneficiary approvals
(iii) five contractors were
appointed for the for the construction of the strucures
(iv) the project was enrolled
with NHBRC (no:29543)
(v) as of December 2015, 995 structures had
been vandalised – including theft of fittings such as doors and toilet units
(table 2).
(vi) 4 foundations are below ground level. The
construction of tarmac roads in future will result in further exersbationof
this problem within the identified sites i.e. a further drop in level
Doors
|
Frames
|
Window
sashes
|
Wash
troughs
|
Tap
|
Cistern
|
Pan
|
|
Phase 1
|
14
|
3
|
4
|
10
|
126
|
9
|
1
|
Phase 2
|
580
|
229
|
589
|
509
|
869
|
403
|
177
|
Total
|
594
|
332
|
593
|
519
|
995
|
412
|
178
|
Table2: Vandalism statistics
Diagram 2: Foundation & Toilets structures
RECOMMENDATIONS
Given the above facts, and
aware of the need to upscale housing delivery in NMBM,the following
recommendations are made;
1.
NMBM appoints a
security firm/s to secure the 1032 sites that have the foundation/toilet
structures but have no beneficiaries on site.
2.
R70m that from the
Provincial Treasury - initially allocated to Coega Development Cooperation – be
redirected to the HDA for construction of houses. This will yield approximately
636 units
3.
HDA appoints a
contractor/s to construct 586 houses – representing the number of beneficiaries
already approved and currently located to their sites.
4.
NMBM urgently
process the remainder of 50 beneficiaries (ie 639-586)
5.
Once 4 above is
completed, HDA appointsa contractor/s to construct the 50 houses
6.
NMBM submits a
funding applications to the Province for the construction of 1035 (being the
difference between the total number of foundations on site and the 636
constructed using the R70m)
No comments:
Post a Comment